Permitting Process
Energy Facilities Siting Board (EFSB):
- Ensures that projects will provide a reliable energy supply, with a minimum impact on the environment, at the lowest possible cost
- Reviews need, alternatives, environmental impacts, costs
- Opportunity for municipal and abutter participation
Anticipated Schedule: 4th Quarter 2022 - 4th Quarter 2024
Permitting Process
Environmental Permitting (not all inclusive):
- Executive Office of Energy and Environmental Affairs Massachusetts Environmental Policy Act Review
- DEP 401 Water Quality Certificate
- Department of Environmental Protection (DEP) Chapter 91 Waterways
- DEP Wetlands Protection Act Order of Conditions
- Department of Environmental Conservation Construction Access Permit
- U.S. Army Corps of Engineers Section 404 General Permit
Anticipated Schedule: 2nd Quarter 2022 1st Quarter 2024
Permitting Process
Local Permitting:
- Municipal Conservation Commissions Wetlands Protection Act Order of Conditions
- Municipal and State Non Environmental Permitting as required (e.g. DOT, DCR, Planning Board, etc.)
Anticipated Schedule: 4th Quarter 2022 4th Quarter 2024